Purchase of Study Schedule Management Program for BA School of Business and Finance

Автор работы: Пользователь скрыл имя, 20 Октября 2013 в 18:22, реферат

Краткое описание

BA School of Business and Finance was established in December 30, 1997 with the Cabinet Order no. 675, although in fact the foundation was laid already in the June of 1992. During its development the institution of higher education has specialized in banking, financial and economics specialist training. Currently BA School of Business and Finance is one of the leading universities in Republic of Latvia that offers both residents and non-residents to acquire professional higher education in the sphere of business, banking and finances. BA School of Business and Finance students, graduates and tutors have gained international recognition for participating in international projects, conferences, for winning scholarship competitions, demonstrated knowledge, skills and abilities for international certification organizations.
The institution of higher education is located in Riga, Kr.Valdemāra 161, and has around 100 employees, that provide top quality educational processes.

Вложенные файлы: 1 файл

Project group work final version.doc

— 808.50 Кб (Скачать файл)

 

  1. Work packages

WORK PACKAGE

Project name:

BA study process planning software acquisition

Work package name:

Task distribution

Work package number:

1110

WP manager:

Dmitrijs Kozlovs

Process Nr.

Process name

Duration (days)

Staff resources

Material resources

1111

Identification of responsibilities under the terms of reference

0,5 days

Project manager, project manager assistants

PC, internet, stationery

1112

Evaluation of project participants

2 days

Project manager, project manager assistants

PC, internet, stationery, HR dept. information, project participants prior work experience

1113

Schedule coordination of project tasks

3 days

Project manager, project manager assistants

PC, internet, stationery

1114

Does all tasks are distributed?

0 days

   

WP result: Project tasks are distributed

 

WP manager:

__________________10.03.2012.

Project manager

_______________10.03.2012.

 
 

signature , date

 

signature , date

 

 

 

WORK PACKAGE

Project name:

BA study process planning software acquisition

Work package name:

Preparation of project documentation

Work package number:

1120

WP manager:

Dmitrijs Kozlovs

Process Nr.

Process name

Duration (days)

Staff resources

Material resources

1121

Development of project documentation

2 days

Project manager

PC, internet, stationery

1122

Development of project documentation templates

0,92 days

Project manager

PC, internet, stationery

1123

Collection of project management documentation

3,82 days

Project manager

PC, internet, stationery

1124

Filling of project documentation templates

8 days

Project manager

PC, internet, stationery

1125

Project documentation templates audit

1 day

Project manager

PC, internet, stationery

1126

Project documentation templates approval

 

1 day

Project manager

PC, internet, stationery

1127

Check if all templates are available

0 days

   

WP result: Project documentation is developed and prepared

 

WP manager:

__________________10.03.2012.

Project manager

_______________10.03.2012.

 

signature , date

 

signature , date

 

 

 

WORK PACKAGE

Project name:

BA study process planning software acquisition

Work package name:

Project co-ordination of financial resources and accounting

Work package number:

1130

WP manager:

Dmitrijs Kozlovs

Process Nr.

Process name

Duration (days)

Staff resources

Material resources

1131

Project finance budget preparation

4,36 days

Project manager

PC, internet, stationery

1132

Project funds approval

7,67 days

Project manager

PC, internet, stationery

1133

Project cost accounting system-money issuance procedures

4,25 days

Project manager

PC, internet, stationery

1134

Project accounting system implementation

67 days

Project manager

PC, internet, stationery

1135

Project accounting systems control development

4,09 days

Project manager

PC, internet, stationery

1136

Project funding and accounting reports creation

3,96 days

Project manager

PC, internet, stationery

1137

Does the project funds are included?

0 days

   

WP result: Project funds are coordinated and accounted

 

WP manager:

__________________10.03.2012.

Project manager

_________________10.03.2012.

 
 

signature , date

 

signature , date

 

 

 

WORK PACKAGE

Project name:

BA study process planning software acquisition

Work package name:

Project interim report creating

Work package number:

1140

WP manager:

Dmitrijs Kozlovs

Process Nr.

Process name

Duration (days)

Staff resources

Material resources

1141

 Project Interim Announcement time

2,11 days

Project manager

PC, internet, stationery, telecommunication s.

1142

 Information gathering for project interim report

4,5 days

Project manager assistants

PC, internet, stationery, telecommunication s.

1143

 Collection of information

6 days

Project manager assistants

PC, internet, stationery, telecommunication s.

1145

 Preparation of interim report

2 days

Project manager assistants

PC, internet, stationery, telecommunication s.

1146

 Interim report, evaluation of project results

1,36 days

Project manager

PC, internet, stationery, telecommunication s.

1147

 Decision on the project interim report evaluation

2,86 days

Project manager

PC, internet, stationery, telecommunication s.

1148

 Does the project interim report developed?

0 days

   

WP result: Interim phase of the project created

 

WP manager:

__________________10.03.2012.

Project manager

_________________10.03.2012.

 
 

signature , date

 

signature , date

 

 

 

WORK PACKAGE

Project name:

BA study process planning software acquisition

Work package name:

Evaluation of project results

Work package number:

1150

WP manager:

Dmitrijs Kozlovs

Process Nr.

Process name

Duration (days)

Staff resources

Material resources

1151

 Project interim report and the overall summary of the results

1 day

Project manager

PC, internet, stationery, telecommunication s.

1152

 Project interim report and the overall analysis of the results

1 day

Project manager

PC, internet, stationery, telecommunication s.

1153

Reporting of the project results, meetings with project participants

10 days

Project manager

PC, internet, stationery, telecommunication s.

1154

 Meeting with project clients

2,22 days

Project manager

PC, internet, stationery, telecommunication s.

1155

 Feedback from the project coordinators

3,33 days

Project manager

PC, internet, stationery, telecommunication s.

1156

Does the project results are evaluated?

0 days

   

WP result: Project results evaluated

 

WP manager:

__________________10.03.2012.

Project manager

_______________10.03.2012.

 
 

signature , date

 

signature , date

 

 

 

WORK PACKAGE

Project name:

BA study process planning software acquisition

Work package name:

Expectation and need understanding, working with coordinators

Work package number:

1210

WP manager:

Ilona Skribiņa

Process Nr.

Process name

Duration (days)

Staff resources

Material resources

1211

Compose the list of needs

0.2 day

Project manager, assistants

PC, internet, stationery, printer

1212

Develop a framework for the operation of the program coordinator

1 day

Project manager, assistants

PC, internet, stationery, printer

1213

Coordinator expected software interface

1 days

Project manager, assistants, IT specialists

PC

1214

Does expectations and needs are understood

0 days

   

WP result: Expectations and needs are understood

 

WP manager:

__________________10.03.2012.

Project manager

_________________10.03.2012.

 
 

signature , date

 

signature , date

 

 

 

WORK PACKAGE

Project name:

BA study process planning software acquisition

Work package name:

Software daily performance description, functionality

Work package number:

1220

WP manager:

Ilona Skribiņa

Process Nr.

Process name

Duration (days)

Staff resources

Material resources

1221

Establishment of software project structure

1 day

Project manager, assistants

PC, internet, stationery, printer

1222

Computer software characteristic development

1 day

Project manager, assistants, IT specialists

PC

1223

Does software characteristics are developed?

0 days

   

WP result: Computer software characteristics developed

 

WP manager:

__________________10.03.2012.

Project manager

_________________10.03.2012.

 
 

signature , date

 

signature , date

 

 

 

WORK PACKAGE

Project name:

BA study process planning software acquisition

Work package name:

Software description  coordination with the coordinators

Work package number:

1230

WP manager:

Ilona Skribiņa

Process Nr.

Process name

Duration (days)

Staff resources

Material resources

1231

Coordinators are aware of the software characteristics, comments

1 day

Project manager, assistants

PC, internet, stationery, printer

1232

Software characteristic revision and implementation of new discussed

1 day

Project manager, assistants, IT specialists

PC, internet, stationery

1233

Does project characteristics agreed with coordinators?

0 days

   

WP result: Software description coordinated with the coordinators

 

WP manager:

__________________10.03.2012.

Project manager

_________________10.03.2012.

 
 

signature , date

 

signature , date

 



 

 

 

 

WORK PACKAGE

Project name:

BA study process planning software acquisition

Work package name:

Selection of software developing company

Work package number:

1240

WP manager:

Ilona Skribiņa

Process Nr.

Process name

Duration (days)

Staff resources

Material resources

1241

Market research

1 day

Project manager, assistants

PC, internet, mobile phone.

1242

Option selection, 3-5 best companies

1 day

Project manager, assistants

PC, internet, stationery

1243

Interviews with selected companies

1 day

Project manager, assistants

Réservations, mobile phone, transportation resources.

1244

Decision-making

1 day

Project manager, assistants, IT specialists

PC, internet, mobile phone, stationery

1245

Does the software development company selected?

0 days

   

WP result: Software development company selected

 

WP manager:

__________________10.03.2012.

Project manager

_________________10.03.2012.

 
 

signature , date

 

signature , date

 

Project budget

 

WORK PACKAGE

Project name:

BA study process planning software acquisition

Work package name:

Software acquisition

Work package number:

1250

WP manager:

Ilona Skribiņa

Process Nr.

Process name

Duration (days)

Staff resources

Material resources

1251

Interview with the selected company, an agreement on software prices

1 day

Project manager, assistants

Reservations, mobile phone, transportation resources.

1252

Software purchase

0.5 days

Project manager, assistants

Unexpected expenses, mobile phone, transportation resources, document preparation costs.

1253

Does the software purchased?

0 days

   

WP result: Software purchased

 

WP manager:

__________________10.03.2012.

Project manager

_______________10.03.2012.

 
 

signature , date

 

signature , date

 

Информация о работе Purchase of Study Schedule Management Program for BA School of Business and Finance