Purchase of Study Schedule Management Program for BA School of Business and Finance

Автор работы: Пользователь скрыл имя, 20 Октября 2013 в 18:22, реферат

Краткое описание

BA School of Business and Finance was established in December 30, 1997 with the Cabinet Order no. 675, although in fact the foundation was laid already in the June of 1992. During its development the institution of higher education has specialized in banking, financial and economics specialist training. Currently BA School of Business and Finance is one of the leading universities in Republic of Latvia that offers both residents and non-residents to acquire professional higher education in the sphere of business, banking and finances. BA School of Business and Finance students, graduates and tutors have gained international recognition for participating in international projects, conferences, for winning scholarship competitions, demonstrated knowledge, skills and abilities for international certification organizations.
The institution of higher education is located in Riga, Kr.Valdemāra 161, and has around 100 employees, that provide top quality educational processes.

Вложенные файлы: 1 файл

Project group work final version.doc

— 808.50 Кб (Скачать файл)



 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

WORK PACKAGE

Project name:

BA study process planning software acquisition

Work package name:

 BA’s computer capacity testing

Work package number:

1310

WP manager:

Martins Stabulnieks, Artjoms Ustinovs

Process Nr.

Process name

Duration (days)

Staff resources

Material resources

1311

Develop a questionnaire

3

Project manager, assistants

PC

1312

Take a survey of students and staff

1

Assistants

PC

1313

Analyse the obtained data

4.92

Project manager, assistants

PC

1314

Conclusion on software potential

1

Project manager

 

1315

Does BA computer system capacity was tested?

0

   

WP result:_________________________________________________________________________________________

 

WP manager:

__________________10.03.2012.

Project manager

_________________10.03.2012.

 
 

signature , date

 

signature , date

 

 

 

WORK PACKAGE

Project name:

BA study process planning software acquisition

Work package name:

Acquisition of the required equipment - UPS, Server

Work package number:

1320

WP manager:

Martins Stabulnieks, Artjoms Ustinovs

Process Nr.

Process name

Duration (days)

Staff resources

Material resources

1321

Look at all the possible offers

5

Project manager, assistants

PC

1322

Impose a decision of the most suitable facility

0,75

Project manager, assistants

Printer

1323

Check equipment compatibility with the rest of the lit

9.25

Project manager, assistants, IT specialist

PC, Service

1324

Check existence of the connection resources

1

Assistants, IT specialist

PC

1325

Software purchase

1

Project manager

PC

1326

Does the software purchased?

0

   

WP result:_________________________________________________________________________________________

 

WP manager:

__________________10.03.2012.

Project manager

_________________10.03.2012.

 
 

signature , date

 

signature , date

 

 

 

WORK PACKAGE

Project name:

BA study process planning software acquisition

Work package name:

 Equipment connection and testing

Work package number:

1330

WP manager:

Martins Stabulnieks, Artjoms Ustinovs

Process Nr.

Process name

Duration (days)

Staff resources

Material resources

1331

Connection of the equipment

0.5

Project manager, IT specialist

 

1332

Test of the connected equipment

3

Project manager, assistants, IT specialist

PC

1333

Analyze the data obtained during the inspection

3

Project manager, IT specialist

PC

1334

Conclusion on the effectiveness of equipment

1

Project manager, IT specialist

PC

1335

Does ​​the connection and equipment tested?

0

   

WP result:_________________________________________________________________________________________

 

WP manager:

__________________10.03.2012.

Project manager

_________________10.03.2012.

 
 

signature , date

 

signature , date

 

 

 

WORK PACKAGE

Project name:

BA study process planning software acquisition

Work package name:

 Program work mode testing

Work package number:

1340

WP manager:

Martins Stabulnieks, Artjoms Ustinovs

Process Nr.

Process name

Duration (days)

Staff resources

Material resources

1341

Program operation mode testing

31.75

Project manager, assistants

 

1342

Analyze the data obtained during testing

20

Project manager, assistants, IT specialist

PC

1343

Conclusion about the effectiveness

6

Project manager, assistants

PC

1344

Does the program work tested?

0

   

WP result:_________________________________________________________________________________________

 

WP manager:

__________________10.03.2012.

Project manager

_________________10.03.2012.

 
 

signature , date

 

signature , date

 

 

 

WORK PACKAGE

Project name:

BA study process planning software acquisition

Work package name:

 Coordinator training planning

Work package number:

1410

WP manager:

Jekaterina Andreimane 

Process Nr.

Process name

Duration (days)

Staff resources

Material resources

1411

 Available space search, reservation

1,5

Assistants

PC

1412

 Time alignment with the coordinators

0,75

Assistants

PC, mobile phone, internet

1413

 Lesson plan and training program compilation

4

Assistants

PC, internet, stationery

1414

 Lesson plan and training program approval

1

Project manager, assistants

PC, mobile phone, internet

1415

Does the lesson schedule is ready?

0

   

WP result:_________________________________________________________________________________________

 

WP manager:

__________________10.03.2012.

Project manager

_________________10.03.2012.

 
 

signature , date

 

signature , date

 

 

 

WORK PACKAGE

Project name:

BA study process planning software acquisition

Work package name:

 Coordinator training conducting

Work package number:

1420

WP manager:

Jekaterina Andreimane

Process Nr.

Process name

Duration (days)

Staff resources

Material resources

1421

 Coordinator level examination

0,1

Assistants

PC, mobile phone, internet

1422

 Lesson schedule alignment with the coordinators

0,1

Assistants

PC, mobile phone, internet

1423

Adaptation of the training program coordinator needs

0,1

IT Specialist

PC, internet

1424

 Training management

5

Assistants

PC, internet

1425

Does the coordinators are well trainers?

0

   

WP result:_________________________________________________________________________________________

 

WP manager:

__________________10.03.2012.

Project manager

_________________10.03.2012.

 
 

signature , date

 

signature , date

 

 

 

WORK PACKAGE

Project name:

BA study process planning software acquisition

Work package name:

 Coordinator skill testing

Work package number:

1430

WP manager:

Jekaterina Andreimane

Process Nr.

Process name

Duration (days)

Staff resources

Material resources

1431

Informing coordinators about the test/ date

1

Assistants

PC, mobile phone, internet

1432

Preparation of the test

0,8

Assistants

PC, mobile phone, internet, stationery

1434

Coordinators testing

0,33

Assistants

PC, internet

1435

Check of the testing results

1

Assistants

PC, internet

1436

Summary of results

1,96

Project manager

PC, mobile phone, internet

1437

Does coordinators skill tested?

0

   

WP result:_________________________________________________________________________________________

 

WP manager:

__________________10.03.2012.

Project manager

_________________10.03.2012.

 
 

signature , date

 

signature , date

 

 

  1. List of events

 

List of events

Costs

BA study process planning software acquisition

Ls 15 391,85

   Project management

Ls 1 855,01

Task distribution

Ls 135,85

Identification of responsibilities under the terms of reference

Ls 10,92

Evaluation of project participants

Ls 50,06

Schedule coordination of project tasks

Ls 74,86

Does all tasks distributed?

Ls 0,00

 Preparation of project documentation

Ls 457,00

Development of project documentation list

Ls 53,01

Development of project documentation templates

Ls 50,25

Collection of project management documentation

Ls 73,36

Filling of project documentation templates

Ls 177,98

Project documentation templates audit

Ls 51,53

Project documentation templates approval

Ls 50,87

Check if all templates are available

Ls 0,00

Project co-ordination of financial resources and accounting

Ls 529,42

Project finance budget preparation

Ls 48,60

Project funds approval

Ls 53,01

Project cost accounting system-money issuance procedures

Ls 96,01

Project accounting system implementation

Ls 225,03

Project accounting systems control development

Ls 55,11

Project funding and accounting reports creation

Ls 51,68

Does the project funds are included?

Ls 0,00

Project intermediary report creating

Ls 435,21

Project Interim Announcement time

Ls 52,34

Information gathering for project interim report

Ls 47,18

Collection of information

Ls 161,98

Preparation of interim report

Ls 64,65

Interim report, evaluation of project results

Ls 53,76

Decision on the project interim report evaluation

Ls 55,31

Does the project interim report developed?

Ls 0,00

Evaluation of project results

Ls 297,52

Project interim report and the overall summary of the results

Ls 54,03

Project interim report and the overall analysis of the results

Ls 53,68

Reporting of the project results, meetings with project participants

Ls 55,31

Meeting with project clients

Ls 81,30

Feedback from the project coordinators

Ls 53,21

Does the project results are evaluated?

Ls 0,00

   Program acquisition

Ls 7 636,11

 Wish and need understanding, working with coordinators

Ls 177,89

Compose the list of needs

Ls 32,61

Develop a framework for the operation of the program coordinator

Ls 82,88

Coordinator expected software interface

Ls 62,40

Does expectations and needs are understood

Ls 0,00

Software daily performance description, functionality

Ls 85,25

Establishment of software project structure

Ls 62,85

Computer software characteristic development

Ls 22,40

Does software characteristics are developed?

Ls 0,00

Software description  coordination with the coordinators

Ls 125,51

Coordinators are aware of the software characteristics, comments

Ls 82,51

Software characteristic revision and implementation of new discussed

Ls 43,01

Does project characteristics agreed with coordinators?

Ls 0,00

       Choice of software developing company

Ls 358,79

Market research

Ls 63,13

Option selection, 3-5 best companies

Ls 82,81

Interviews with selected companies

Ls 112,70

Decision-making

Ls 100,16

Does the software development company selected?

Ls 0,00

       Software acquisition

Ls 6 888,67

Interview with the selected company, agreement on software prices

Ls 97,70

Software purchase

Ls 6 790,97

Does the software purchased?

Ls 0,00

   Introduce of the software and adaptation for work

Ls 5 446,80

BA’s computer capacity testing

Ls 323,20

Develop a questionnaire

Ls 96,00

Take a survey of students and staff

Ls 22,40

Analyze the obtained data

Ls 164,80

Conclusion on software potential

Ls 40,00

Does BA computer system capacity was tested?

Ls 0,00

       Acquisition of the required equipment - UPS, Server

Ls 1 681,00

Look at all the possible offers

Ls 145,70

Impose a decision of the most suitable facility

Ls 38,00

Check equipment compatibility with the rest of the lit

Ls 1 319,00

Check existence of the connection resources

Ls 37,40

Software purchase

Ls 140,90

Does the software purchased?

Ls 0,00

       Equipment connection and testing

Ls 271,60

Connection of the equipment

Ls 25,00

Test of the connected equipment

Ls 149,40

Analyze the data obtained during the inspection

Ls 59,80

Conclusion on the effectiveness of equipment

Ls 37,40

Does ​​the connection and equipment tested?

Ls 0,00

       Program work mode testing

Ls 3 171,00

Program operation mode testing

Ls 1 860,00

Aanalyzer the data obtained during testing

Ls 1 116,60

Conclusion about the effectiveness

Ls 194,40

Does the program work tested?

Ls 0,00

Training process

Ls 453,94

       Coordinator training planning

Ls 173,23

Available space search, reservation

Ls 33,60

Time alignment with the coordinators

Ls 17,40

Lesson plan and training program compilation

Ls 79,23

Lesson plan and training program approval

Ls 43,01

Does the lesson schedule is ready?

Ls 0,00

       Coordinator training conducting

Ls 134,97

Available space search, reservation

Ls 2,32

Time alignment with the coordinators

Ls 2,32

Lesson plan and training program compilation

Ls 15,30

Lesson plan and training program approval

Ls 115,03

Does the lesson schedule is ready?

Ls 0,00

       Coordinator skill testing

Ls 145,74

Coordinator level examination

Ls 23,21

Lesson schedule alignment with the coordinators

Ls 34,34

Adaptation of the training program coordinator needs

Ls 7,68

Training management

Ls 23,01

Are the coordinators goodl trainees?

Ls 57,51

Coordinator level examination

Ls 0,00


 

 

 

 

  1. Resource plan

 

Resource name

Quantity

Costs

Variable

Fixed

Project manager

1

Ls 5,00/h

Ls 0,00

Paper

 

Ls 2,10

Ls 0,00

IT specialist

2

Ls 0,00/h

Ls 15,00

Internet

1

Ls 12,10/month

Ls 0,00

Stationery supplies

 

Ls 10,00

Ls 0,00

Computer

3

Ls 0,30/h

Ls 0,00

Printer

1

Ls 0,30/h

Ls 0,00

Assistant

1

Ls 2,50/h

Ls 0,00

Mobile phone

3

Ls 4,00/month

Ls 0,00

Server

1

Ls 0,00/h

Ls 800,00

Scanner

1

Ls 0,30/h

Ls 0,00

Transportation expenses

 

Ls 0,00

Ls 2,67

Meeting place reservation

1

Ls 0,00

Ls 50,00

Document preparation/ arranging costs

 

Ls 0,00

Ls 45,00

Unforeseen expenses (10%)

 

Ls 0,00

Ls 213,30

Programming costs

 

Ls 0,00

Ls 6 500,00

Unforeseen expenses (~10-15%).

 

Ls 0,00

Ls 810,00

Purchase of goods

 

Ls 0,00

Ls 100,00

Maintenance

 

Ls 0.00

Ls 180.00


 

Информация о работе Purchase of Study Schedule Management Program for BA School of Business and Finance